In stunning reversal common council votes to keep current airport and cease expansion efforts
Posted: Fri Sep 29, 2023 6:29 pm
Portage -
In February 2021 Engineering and architecture planning firm TKDA of St. Paul held the virtual public meeting. Group Manager of Aviation Planning Marcus Watson laid out three options for the city.
In July 2021 a new Airport Master Plan was developed. It identified growth in aviation activity including new based aircraft and larger business aviation aircraft is constrained by the size of the current facilities.
The following previous studies had been commissioned.
1972 – Airport Site Selection Study
1992 – Airport Site Selection Study
1994 – Runway Feasibility Study
2002 – Airport Feasibility Study (Phase 1)
2003 – Airport Feasibility Study (Phase 2)
2007 – Environmental Assessment for new Airport
2011 – Airport Master Plan Update
.ad.
Staring with the 1972 study the recommendation has been to move the airport. The current master plan identifies minimum runway length is about 2,800 feet, the average runway length is 3,100 feet, and at least 5,000 feet is needed for corporate aircraft (insurance).
In a August 2023 Columbia County News and Events poll, 55% of respondents want a new airport. After push-back from citizens on proposed action to close the airport at the September 14th common council meeting the proposed action was voted down. Mayor Craig stated "I would encourage this council to accept all the money that we possibly can to make the airport that we have right now as nice as we possibly can. I'm going to be instructing City staff to invest no more time or effort into looking at a new airport but to spend all their time and effort to make the airport we have as nice as we can".
In February 2021 Engineering and architecture planning firm TKDA of St. Paul held the virtual public meeting. Group Manager of Aviation Planning Marcus Watson laid out three options for the city.
- Option A, which was suggested by the Airport Commission, the airport master plan would be implemented for $8.6 million in airport improvements with roughly $660,000 in costs to the city.
- Option B outlined the closure of the airport due to its deficiencies.
- Option C explores the possibility of a new airport site.
In July 2021 a new Airport Master Plan was developed. It identified growth in aviation activity including new based aircraft and larger business aviation aircraft is constrained by the size of the current facilities.
The following previous studies had been commissioned.
1972 – Airport Site Selection Study
1992 – Airport Site Selection Study
1994 – Runway Feasibility Study
2002 – Airport Feasibility Study (Phase 1)
2003 – Airport Feasibility Study (Phase 2)
2007 – Environmental Assessment for new Airport
2011 – Airport Master Plan Update
.ad.
Staring with the 1972 study the recommendation has been to move the airport. The current master plan identifies minimum runway length is about 2,800 feet, the average runway length is 3,100 feet, and at least 5,000 feet is needed for corporate aircraft (insurance).
In a August 2023 Columbia County News and Events poll, 55% of respondents want a new airport. After push-back from citizens on proposed action to close the airport at the September 14th common council meeting the proposed action was voted down. Mayor Craig stated "I would encourage this council to accept all the money that we possibly can to make the airport that we have right now as nice as we possibly can. I'm going to be instructing City staff to invest no more time or effort into looking at a new airport but to spend all their time and effort to make the airport we have as nice as we can".